Skip to content

Sprint 2 review: implementation and validation

How to use: the Product Owner runs the review on Wed 2026-10-28. Every rubric bullet must link to evidence in this repository. Rubric weight: 20%.

Date: 2026-10-28. Product Owner: Allie Hodges. Scrum Master: Hina Kramer. Present: [ ] Leticia Aderhold [ ] Jerad Dunne [ ] Allie Hodges [ ] Hina Kramer [ ] Instructor (if present)

Sprint goal check

  • Sprint goal (from planning):
  • Met: yes / partially / no. Explain in two sentences:

Rubric review checklist (verbatim from the assignment)

The Sprint 2 review must include:

  • A working implementation of the core mining, extraction, similarity, classification, traceability, or visualization method. Evidence:
  • Automated tests for important parsing, transformation, matching, or metric functions. Evidence:
  • A validation sample, manual annotation protocol, or other evaluation design. Evidence:
  • Preliminary results with reproducible figures or tables. Evidence:
  • At least one pull request reviewed by a different team member than the author. Evidence (link the PR and its approving review):
  • An updated research report containing the background, method, implementation, and preliminary results. Evidence:
  • A retrospective that records changes to the research question, method, scope, or interpretation. Evidence:

Sprint 2 acceptance criteria (verbatim)

Criterion Pass / Fail Evidence link Notes
The core implementation runs end to end on the approved sample
The method is tested
The group can explain why the result should be trusted or where it may fail
The preliminary analysis is supported by generated evidence rather than screenshots alone

Validation status

Kind Primary rater Second rater Second-rater labels committed (PR #, date) Primary labels committed after (PR #, date) Cohen's kappa
Signals jd
Lineage jd
Drift jd

Demo script (12 minutes)

Step Content Time Presenter
1 Restate the question and the method in two sentences 1 min
2 Fresh terminal: make test then make pipeline; show CI status 3 min
3 One preliminary table and one figure, naming the script that produced each 3 min
4 Validation protocol, precision per rule, and inter-rater agreement between the primary and second rater 2 min
5 One PR with its cross-member review, the ADR for the main design decision, and the metrics dashboard 2 min
6 Where the result may fail and what Sprint 3 will do about it 1 min

Gemba walk: fresh-clone reproduction record

Field Value
Who (a member who did not write the README) and environment
Date
Commit SHA
Steps followed (from README)
Time to first result (minutes)
Result matched committed output yes / no
Problems found (open issues)

Instructor feedback

Feedback Action Owner Issue #

Velocity and KPIs at review

Metric Sprint 1 Sprint 2
Points planned / completed
Issues closed
PRs merged / merged with an approving review from another member
Median PR first-review turnaround (hours)
Median cycle time (days)
Median PR open-to-merge time (hours)
CI pass rate
Rework items
Contribution share per member (min / max)
Test count / coverage

Backlog changes agreed at the review

  • Added:
  • Removed or cancelled:
  • Re-estimated: