Lean Six Sigma overlay

Scrum gives this project its delivery cadence: three sprints, a backlog, planning, reviews, and retrospectives. Lean Six Sigma (LSS) adds a measurement and improvement discipline on top of that cadence. Scrum decides what is shipped and when. LSS decides how to know the process is healthy and how to fix it when it is not.

The rubric grades "Scrum practice" on whether planning, reviews, retrospectives, and backlog evolution are "visible and used to improve the work". LSS makes the "used to improve" part measurable rather than anecdotal. The project is run by the four-person Group 9 (ADR-0006); section "Group notes" lists what that means for the tools below.

The two layers

Layer Owns Cadence Evidence
Scrum Backlog, sprint goals, roles, ceremonies, Definition of Done Sprint (3 weeks), weekly check-in, Mon/Wed/Fri stand-ups GitHub Issues, Project board, docs/sprints/
Lean Six Sigma KPIs, control charts, root-cause analysis, waste removal, risk register, tollgates Weekly metrics snapshot, per-sprint tollgate, per-retro root cause docs/lean-six-sigma/, metrics/DASHBOARD.md, kaizen issues

Where each LSS tool is used

LSS tool Scrum ceremony or artifact where it is used File
DMAIC roadmap Sprint boundaries (each sprint is one DMAIC phase with a tollgate) DMAIC.md
SIPOC and CTQ tree Formation and Sprint 1 planning (defines the pipeline and what quality means) SIPOC_AND_CTQ.md
KPI catalogue Thursday check-in, sprint review KPIS.md
XmR control charts and run rules Thursday check-in metrics/README.md, metrics/charts/
Value stream map Sprint 1 retrospective, revisited in Sprint 3 VALUE_STREAM_MAP.md
DOWNTIME waste log Any stand-up, formally reviewed at the retrospective WASTE_LOG.md
FMEA risk register Sprint planning (review top RPN items), sprint review (update) FMEA_RISK_REGISTER.md
5 Whys and fishbone Retrospective, or whenever a control chart signals ROOT_CAUSE_TEMPLATE.md
A3 problem solving Retrospective actions too big for one kaizen issue A3_TEMPLATE.md
Kaizen backlog Retrospective output, tracked as kaizen issues KAIZEN_BACKLOG.md
Control plan and gemba walk Sprint review (reproducibility walk by a non-author), Finalization CONTROL_PLAN.md

Weekly rhythm

Day What happens LSS input
Sunday 06:00 UTC GitHub Actions runs the LSS metrics workflow and opens a PR on branch metrics/weekly Fresh snapshot, dashboard, charts
Monday Scrum Master reviews the metrics PR; another member approves and it is merged; stand-up Dashboard status column
Wednesday Stand-up Waste log entries if any
Thursday Team check-in and metrics review (15 minutes) KPI table, run-rule signals, open blockers, contribution flags, top 3 FMEA risks
Friday Stand-up; Scrum Master week summary PRs waiting more than 48 hours for review
Last Wednesday of the sprint Sprint review, then retrospective Tollgate checklist, 5 Whys on the worst signal, kaizen items created

Group notes (ADR-0006)

Element Status Notes
Contribution-balance KPI Active; band [0.15, 0.45] in project.yml Read at every check-in; a flag starts a rebalancing conversation
PR first-review turnaround Active; target 48 hours Matches the 48-hour review SLA in the charter
PR open-to-merge cycle time Active as an extra KPI; target 96 hours Kept from the short solo period because it shows where merged work waits
Cross-member review Required; main needs one approving review from another member First-time-right is read with the review comments
Stand-ups Written by all four members on Monday, Wednesday, and Friday docs/meeting-notes/YYYY-MM-DD-standup-week.md
Measurement system check Two members run the pipeline independently on different machines Sprint 1 item S1-10
Rater agreement Primary rater plus a teammate second rater; inter-rater Cohen's kappa docs/validation/README.md

Owner roles in these documents (Product Owner, Scrum Master, Developers) follow the rotation in project.yml.

10-minute quick start for a reader

  1. Read KPIS.md. The summary table says what is measured and what good looks like.
  2. Open metrics/DASHBOARD.md. If it says "no data yet", the first snapshot has not run.
  3. Read DMAIC.md for the current sprint only. The tollgate checklist is what the sprint review checks.
  4. Skim the top five rows of FMEA_RISK_REGISTER.md sorted by RPN.
  5. Look at WASTE_LOG.md and KAIZEN_BACKLOG.md to see what slowed the work and what was changed.
  6. To regenerate the dashboard locally:
pip install -e ".[dev]"
export GITHUB_TOKEN=<a token with repo read access>
python scripts/lss_metrics.py --repo jeraddunne/csc580-group9-msr2027

The output lands in docs/lean-six-sigma/metrics/. Commit it on a branch and open a PR labeled type:process.

Rules of thumb

  • Metrics are for the process, not for judging people. Their job is to show honestly where time went and whether changes helped.
  • A control chart signal is a question, not a verdict. It triggers a 5 Whys, nothing else.
  • Every retrospective produces at least one kaizen issue or an explicit note that none was needed.
  • Targets in project.yml may be changed at a retrospective; record the change in docs/workspace/DECISION_LOG.md.