Formation planning (Define phase)

How to use: the Formation Scrum Master keeps this list current until 2026-09-16. Every row needs an owner and a completion date. Move anything unfinished into Sprint 1 planning with a note. The project was briefly solo on 2026-09-14 (ADR-0005); the four-person group was reinstated on 2026-09-15 (ADR-0006), so the group rows are active again.

Period: Thu 2026-09-10 to Wed 2026-09-16. Rubric weight: 10% (topic selection, research question, initial backlog). Product Owner and Scrum Master for formation: Jerad Dunne.

Formation goal

Form the team, inspect the data, confirm the research question, and leave Sprint 1 with a repository, a charter signed by all four members, an approved topic brief, and an estimated initial backlog.

Checklist

# Item Evidence Owner Target date Done date Status
F1 Repository created from the recommended structure, public, instructor has access Repo URL Jerad Dunne 2026-09-13 2026-09-13 [x]
F2 Every member accepted the repository invitation and has board write access Collaborator list Each member 2026-09-16 [ ]
F3 Every member completed a Team member onboarding issue 4 closed onboarding issues Each member 2026-09-16 [ ]
F4 Every member added a profile in docs/team/ in their first pull request 4 profiles Each member 2026-09-17 [ ]
F5 Team charter v2.0 (TEAM_CHARTER.md) signed by all four, each in their own onboarding pull request Section 14 signature rows Each member 2026-09-17 [ ]
F6 Dataset sample downloaded and inspected (make data) data/samples/MANIFEST.json; findings F-006 to F-012 Jerad Dunne; each member runs make data 2026-09-16 [ ]
F7 Topic proposal written Issue #41, docs/proposals/P-01-jerad-dunne-skill-risk-propagation.md Jerad Dunne 2026-09-14 [ ]
F8 Ballots cast and tally run Retired: P-01 was selected directly (ADR-0004) - - - n/a
F9 Topic decision record docs/decisions/ADR-0004-topic-selection.md Jerad Dunne 2026-09-14 [ ]
F10 Group reinstated and recorded docs/decisions/ADR-0006-group-reinstated.md Jerad Dunne 2026-09-15 [ ]
F11 P-01 confirmed by the group, or a Decision needed issue opened to revisit it Kickoff notes or decision issue Each member 2026-09-17 [ ]
F12 RESEARCH_QUESTION.md filled: question, motivation, unit of analysis, population, variables, competing explanation File merged after review by another member Product Owner 2026-09-17 [ ]
F13 Repository settings: branch protection on main (PR required, 1 approving review, squash only), labels, milestones with due dates Link to rules Jerad Dunne 2026-09-15 [ ]
F14 GitHub Project board created from the instructor template (statuses Todo, In progress, Done, Block, Cancelled; Sprint and Estimate fields) and linked to the repo Project URL in README Jerad Dunne 2026-09-16 [ ]
F15 Initial backlog: Sprint 1 rubric deliverables as issues with acceptance criteria, owners, estimates, milestone Sprint 1 Milestone shows issues Product Owner 2026-09-16 [ ]
F16 Roles confirmed for all sprints (see docs/sprints/README.md) Kickoff notes, project.yml Team 2026-09-16 [ ]
F17 Second rater chosen for each validation kind (signals, lineage, drift) docs/workspace/WORK_SIGNUP.md section 6 Team 2026-09-16 [ ]
F18 Sprint 1 work sign-ups filed Work sign-up issues Each member 2026-09-16 [ ]
F19 Topic brief submitted to the instructor (question, dataset, approach, team, backlog link) Submission record Product Owner 2026-09-16 [ ]
F20 FMEA risk register reviewed, including group risks docs/lean-six-sigma/FMEA_RISK_REGISTER.md Scrum Master 2026-09-16 [ ]
F21 AI-use log up to date ai-use-log.md Each member 2026-09-16 [ ]

Define phase exit criteria (DMAIC)

  • Problem statement and research question are written in one sentence each and agreed by all four.
  • Customer of the work is named (instructor rubric criteria, and the MSR research community as secondary).
  • Critical-to-quality items are listed in docs/lean-six-sigma/KPIS.md and match the rubric quality criteria.
  • Scope is bounded: dataset, sample, and what is out of scope are recorded in RESEARCH_QUESTION.md.
  • SIPOC for the pipeline exists (docs/lean-six-sigma/SIPOC_AND_CTQ.md).

Notes and carry-over

  • Items not done by 2026-09-16 (list issue numbers):
  • Reason and new date: